Main
/
News
/
14 MW Solar Power Plant Construction Update

14 MW Solar Power Plant Construction Update

05/05/2026

 

14 MW SPP — when scale is measured not only in megawatts, but also in pace.

 

14 MW of capacity. Hundreds of meters of trenches. Thousands of connections. And the #EDS team, on-site every single day — working without pause.

 

☀️ Phase 1 (9 MW) — Fully Completed:

PV Modules: solar panels are fully mounted and positioned on support structures;

 

Cable Networks: trenches are dug, the sand bedding is prepared, and backfilling is complete;

 

10 kV Infrastructure: high-voltage line is connected to the grid;

 

Equipment: DC/AC inverters are fully connected and operational, power cables are connected to the package transformer substation (PTS);

 

Installation Works: cable trays and support-mounted cabinets are installed;

 

Security & Logistics: site lighting and video surveillance are ready, on-site roads and tracks are graded;

 

General Civil Works: foundation waterproofing is completed.

 

⚡ Phase 2 (5 MW) — In the Final Stages:

PV module installation — 90%

PV cable routing — 80%

Power cable routing — 80%

Cable routing from PTS to the closed switchgear (CSG) — 80%

Earthworks (trenches, sand bedding) — 90%

Trench backfilling — 70%

CSG grounding loop — 80%

DC/AC inverter connection — 50%

Auxiliary power cable routing (lighting, surveillance) — 70%

Cable termination in PTS — 50%

Backfilling of the battery room and warehouse foundations — in progress ⏳

 

We are approaching the finish line — soon this 14 MW solar power plant will start generating clean energy and driving returns! 💪