Construction of a 100 MWh wind farm: strengthening Ukraine's energy system

Construction of a 100 MWh wind farm: strengthening Ukraine's energy system

08/10/2025

 

The construction of an energy storage unit (ESU) with a capacity of 100 MWh and a capacity of 50 MW is in full swing!

 

⚡️ We are actively working on key stages that bring the launch of an important facility for the Ukrainian power system closer.

 

Main achievements:

✅ 110/35 kV power transformer:

- All attachments have been assembled.

- The transformer is filled with oil.

- High-voltage tests were carried out.

- The oscillation on the 110 kV side was completed.

 

✅ High-voltage equipment:

35 kV metal supports and 110 kV cable couplings were installed.

- The 110 kV switchgear was completed.

- Installation in the cells of the GIS and the switchgear for connection to the grid was completed.

 

✅ Infrastructure:

The foundations for the GIS are ready.

- The modular building of the automatic transfer switchgear was installed.

- Landscaping near the 110 kV outdoor switchgear has been completed.

 

✅ Cable networks and control:

0.4 kV cables and secondary circuits for the first stage have been laid.

- Control cabinets have been installed at the outdoor switchgear.

- Laying of 0.4 kV cable for the second stage is in progress.

- Installation of cables for the second stage and connection of secondary circuits is completed.

 

We are confidently moving forward!

 

The next stage is the installation of the main equipment of the RCD and preparation for commissioning.