🔌 EDS-Ukraine Powers New Water Pipeline to Mykolaiv from the Southern Bug River
A new water supply system for Mykolaiv - #EDS_Ukraine provides the energy component of the project!
The construction of a large-scale water pipeline from the Pivdennyi Buh River in the New Odesa area is underway to provide Mykolaiv with clean water after the destruction of the Kakhovka HPP. And we, #EDS-UKRAINE, are proud to be involved in the implementation of this important project! 🚧
💪 What we do.
#EDS_Project - we have developed project documentation for the energy infrastructure that will ensure reliable power supply.
#EDS_Power is a manufacturer of switchboard equipment for gas compressor stations
#EDS_Engineering - we carry out the construction of power grids:
🔸 Two 35 kV power lines (main and backup) for each pumping station, which guarantee category II reliability.
35 kV switchgear (RU-35 kV) of our own production at each pumping station.
Air-cable transitions together with 35 kV reclosers for connection to Mykolaivoblenergo networks.
⚡️ The power we provide:
✔️ VNS-1: 3120 kW
✔️ VNS-2: 1600 kW
✔️ VNS-3: 1600 kW
🏢 All power grids and pumping stations are located in fortified premises designed to be safe even in the face of hostilities.
This project is a contribution to the recovery and stability of the region.