EDS: construction progress of the Sense City residential complex.
Have you forgotten that the #EDS team is not only engaged in the construction of energy facilities, but also implements modern civil engineering projects?
Today we are sharing an update from the construction site of the Sense City residential complex.
Our team is performing monolithic works, general construction works, as well as masonry of internal and external walls - all in compliance with high quality standards and construction rates.
🔸 The monolithic works in sections 6 and 7 are fully completed, and in section 5 the team has reached the 4th floor of the monolithic frame, steadily increasing the pace.
🔸 Wall masonry: section 3 is in progress - 4 out of 7 floors have been completed; masonry in sections 1, 2, 6 and 7 has been completed.
Each floor is the result of tireless work in creating a space where every meter has its own meaning.