EDS COMPLETED THE RECONSTRUCTION OF THE 35/6 KV SS SEVERNAYA

EDS COMPLETED THE RECONSTRUCTION OF THE 35/6 KV SS SEVERNAYA

22/09/2020

The EDS team carried out the technical re-equipment of the 35/6 kV SS Severnaya in Zhovti Vody city (Dnipropetrovsk oblast). The whole complex of works took 26 days.

The power transformer was replaced: instead of TMN-3200/35 kVA, a TMN-4000/35 kVA was installed;

The construction part of the oil receiver and the transformer foundation has been completed fully.

The relay part of the transformer was completed: a relay protection cabinet manufactured by EDS was installed, the busbars of the HV and LV transformers was replaced.

Commissioning works have been carried out.

Regarding the RZiA (relay protection and automation) cabinet. The switchboard link of the EDS group - the #EDS_Power plant - has mastered the production of all-welded stainless steel boards - with powder coating and zinc plating. These boards can be used in any sector of industry. We will tell you more about this in one of the following news.

Outdated equipment was replaced with the new one - more powerful, efficient, reliable;

consumers in the region are the population, schools, hospitals, kindergartens - have received more reliable energy supply.