19/01/2021

We are proud to announce the construction of a 110/35 kV high-voltage electric substation "Yuzhne Energy" in Lymanskyi district, Odessa region. The customer of the facility is JSC "DTEK Odessa Electric Networks".

This is the second, facility after 330/35 kV SS Nadezhdyne in Zaporizhia region, which we are building from scratch.

It should be noted that EDS will carry out a full range of preparatory, construction and installation works for the construction of a power distribution scheme for the future 76.5 MW wind power station.

EDS's participation as a builder of complex network infrastructure facilities in the country is an indicator of the large customers’ confidence in the accumulated expertise of our team and a consistently high level of work performance.

Below is a small snapshot of what is happening right now at the construction site.

  • Installation of the attachable equipment on the T2 power transformer;
  • Outdoor cabinet installation: YaZV 90 – 2 pcs.; YaZV 30 – 1 piece.; YaZ – 1 piece;
  • Replacement of the generator for degassing oil on power transformers;
  • Manufacturing of metal structures for the 110 kV ZON drive fixing;

High-voltage tests of T1 and T2 transformers at the site are carried out by the team of the EDS mobile electrotechnical laboratory – ETL-35K.

Order tests: +38 050 014 31 02 or etl@eds-ltd.com.ua

Resources:

  • Technical and engineering employees: 11 people;
  • Workers: 10 people;
  • Specialized machinery from EDS own fleet: JCB 4 – 1 unit, BobCat – 2 units.