Comprehensive Approach and Rapid Solutions by EDS-Project for 10 MW Solar Power Plant Construction

Comprehensive Approach and Rapid Solutions by EDS-Project for 10 MW Solar Power Plant Construction

13/11/2024

🔆 10 MW solar power plant: An integrated approach and quick solutions from EDS-Project 

When working on such large-scale projects as a 10 MW solar power plant, the primary task of the EDS-Project was to quickly provide solutions for the prompt start of construction. We started the process by developing the Main Technical Solutions (MTS), a key stage that allows us to parallelize the maximum number of processes and significantly reduce the implementation time.

🔹 What does the OTS include?

• PVsyst modeling of the solar power plant to select the configuration of the technological part, which ensures the ordering of PV modules and inverters.

• Site planning and development of "table" designs for ordering metal structures for PV mounting systems and perimeter fencing.

• Single-line diagram and equipment selection with questionnaires for placing orders for long-term equipment.

• Design of equipment placement and connections for the advance purchase of cable and wire products.

🔹 In addition, we created a complete set of design and estimate documentation, which included engineering solutions for the construction of 10 solar stations of 1 MW each with their connection to the networks of JSC "Vinnytsiaoblenergo". Due to the complex engineering and geological conditions, the project was examined for strength, reliability, and durability.

It is important for us that the project not only meets the technical and economic requirements of the Customer, but also is convenient, safe in operation and as efficient as possible. EDS-Project works to ensure that each solution leads to the implementation of facilities with high reliability and uninterrupted operation.