We are changing the energetics. The “Donetsk four”: the beginning
This could be the title for some kind of blockbuster.
However, everything is even cooler: the EDS energy group begins preparatory work on the implementation of four technical re-equipment facilities in the Donetsk oblast — the so-called “Donetsk Four”. The EDS team has already visited all sites to assess the scope of work.
Here is a list of substation upgrade works that will be performed by EDS:
110/35/6 kV “Bakhmutskaia” substation - replacement of the existing 6 kV outdoor switchgear with a new KRUM-6 type;
110/35/6 kV “Novoraiskaia-110” substation - complete reconstruction of 35 kV ORU (outdoor switchgear),
reconstruction of RZiA (relay protection and automation) of the 35 kV side and reconstruction of outdoor lighting;
110/35/6 kV “VAOK-110” substation - reconstruction of 6 kV busbar bridges,
reconstruction of ZRU-6 kV indoor switchgear and 6 kV power cables re-laying;
RP-16 distribution point in Kramatorsk - reconstruction of equipment, namely: KSO I, KSO II cells, ShchO-90 panels and TMH 630/1 power transformers.
Now each of the facilities is in the active phase of purchasing the necessary materials and equipment.