We inform about the start of the project on laying a 6 kV cable line in Dnipro.

We are talking about the technical re-equipment of 6 kV voltage cable lines KL with dispatch control of the SS «PLM 13 – RP Lider 17». All works EDS-ENGINEERING performs as a general contractor.

Already at the beginning of the summer of this year, the team of EDS-ENGINEERING specialists will complete a full range of works on laying a 6 kV cable line with a path length of 2151 meters, connecting the cable to the contact bars of the electrical installation, installation of terminal and coupling boxes, as well as the final site improvement.

It should be noted that all works involving specialized machinery from our own vehicle fleet are performed by an experienced and well-equipped E-Cable team, whose specialization is underground cable lines. In more detail about this team and a set of equipment we will tell in one of the following publications.