Main
/
UNFREEZING. EDS IS BUILDING A NEW LARGE SPS

UNFREEZING. EDS IS BUILDING A NEW LARGE SPS

09/09/2020

The EDS Group has started the turnkey construction of a new industrial solar power station with a capacity of 9.99 MW in the Zaporizhia oblast.

The future SPS will be built in the area of Dniprorudne city, Vasylivskyi district, Zaporizhia oblast.

EDS Project (EDS project link), EDS Engineering (construction of energy facilities), EDS Power (production of switchboard equipment) are involved in the work on the solar power station. At later stages, the team of the electrotechnical laboratory ETL-35K will join to conduct high-voltage tests of the facility's power equipment.

Now marking and drilling of holes for the PV modules rackings' posts and fences continues at the construction site of the facility, concreting of the posts and work has begun for the installation of KTP (packaged transformer substation) (excavation of the pits, preparation of the reinforcing bars).

Note that the full construction cycle will take a little more than two months, and by the end of October the work at the facility will be completed.