Greenhouse plant power supply system modernization
Technical
features
features
Type of
works
works
Video
- Length of strip lines: 5292 m;
- Underground line: 4491 m;
- Air line: 801 m
Installed :
- 20 supports - СВ105-5;
- 9 supports - СК105-10;
- 14 racks - USO-5A;
- MODULE KTP-630;
- RU-10 kV series MVC-10;
- RU 0,4 kV of the StreamLine;
- Arrangement of sand bags;
- The conducted works on installation of cable trenches;
- Laying of warning tape;
- Supply and commissioning of packaged transformer substation with two transformers with capacity of 630 kVA with a partition scheme for the high voltage.;
- Installation 8 KTP -1000 on the Foundation;
- For additional protection of the cable on the track produced pipe PE 90 in the area of route length of more than 1000 m;
- Installation of an 8-power transformer of type TMG-1000/10.