Reconstruction of substation 150 kW «Ochistnye Sooruzheniya»
Type of
works
works
Video
- Laying of cables and overhead lines has been done;
- Dismantling of equipment in the cells of the T-32 and L-525, to perform the further reconstruction of the cells, has been done;
- A complete set of necessary cells of the current-limiting reactor was made;
- Installation of two disconnectors of 35 kV, VkV35 in a quantity of 1 piece and TT35 - 3 pieces, OPN-35 in a quantity of 3 pieces were completed in cell L-525.
- Assembled microcontroller for monitoring of the processes;
- Grounding devices for T-32, L-525 cells and reactor cells were installed;
- Installation of cable channels in cells T-32, L-525 has been done.