Reconstruction of outdated equipment for substation «Liteinaia»
Power:
150 kV
Type of
works
works
Reviews
Video
- Replacement of 8 disconnectors RNDZ-220, RNG-220 with the possibility of remote control from the control room has been carried out;
- Laying a control cable longer than 19 km.
- Commissioning and high-voltage tests using our own mobile laboratory ETL-35K;
- Installation of a new tray system of precast concrete.