Reconstruction of the cable line Frunzenskiy housing estate
Technical
features
features
Type of
works
works
Video
Length of strip lines: 770 m
- Replacement of cable line (CL) between TP-and TP 1551-1553
- Cable laying was carried out by underground method. For the reconstruction of the used cable with XLPE insulation cross-section 120 mm (Apvegap 1*120/25).
-
Cable laying was carried out in conditions of dense urban development. The most difficult part of KL was on the territory of Parking. Because of the intersection of KL with the heating pipes, gas pipelines of low and medium pressure arose the necessity of deepening to a depth of 3.5 meters.