SPS 2 MW «Alanta Energy»

Power: 2 MW
Area: 4 ha
The construction period: 10.2018 - 12.2018
Start generated: 04.2019
0 Technical
features
1 Type of
works
2 System
protection
3 Conditions
operation
4 Reviews
5 Video
0
  • Installed capacity of photovoltaic modules — 2,3 MW;
  • Inverter capacity of station – 2,0 MW;
  • The volume of annual electricity generation is 2518 MW/year;
  • CO2 reduction – 4377 tons;
  • The number of “Jinko Solar” photovoltaic modules (PV modules) – 4200 pcs. with a capacity of 270 W;
  • The number of “Talesun” photovoltaic modules (PV modules) – 3600 pcs. with a capacity of 325 W;
  • The number of «Huawei» inverters – 50 pcs. 40 kW each;
  • The number and power of EDS combiners — 6 units of 160 kW each; 6 units of 170 kW each;
  • The number of transformer substations MODULE 1000/6/0,4 – 11 pcs.

 

Appointment:

  • Conversion of solar energy to ~ 6000 V, 50 Hz electric power and its transmission to the electricity grid to other consumers.

 

Accounting for electricity:

Bidirectional counter:

  • on generation networks - EPQS 122.23.17 LL;
  • on your own - GAMA 300 G3B.
1
  • Feasibility study design;
  • Development of the design documentation;
  • Supply of solar panels and inverter equipment;
  • Supply of power and switchboard equipment;
  • Construction and installation works;
  • Connection of the constructed SPS to the grid;
  • Member registration in WEM and “green” tariff approval;
  • Service maintenance of SPS.
2

0.4 kV AC power supply:

  • 0.4 kV input switch - LZMN4-AE1600 1600 F (EATON);
  • surge suppressors - ETITEC B 320 / 12,5 F (ETI).

 

6 kV AC power supply:

  • vacuum switch BB / TEL-10/630 (Tavrida Electric);
  • load switches BHA-10/630;
  • surge suppressors - OPN-KR / TEL-6 / 7.2 kV.
3

When operating a solar power plant:

  • the conditions and operating requirements of the equipment provided by its manufacturers in the relevant instructions must be observed;
  • Before switching on the equipment, make sure that it is not mechanically damaged;
  • it is advisable to periodically perform maintenance work on the equipment as recommended by its manufacturer;
  • Appropriate safety measures must be followed.
4
SES «Alanta Energy»
Review of «Alanta Energy» on the implementation of a range of construction and installation work on the construction of a solar power plant with capacity of 2 MW.
5
Video
Want to build a similar project, but don't know where to start? Request a manager consultation
or
Fill out the brief
Customer profile
Industrial Solar Power
placement:
Services you need:
Order project