Reconstruction of electrical substations «Sinelnikovo-1»

0 Type of
works
0
Type of
works
  • Installed 14 units of production EDS MVC and bus bridge 10 kV;
  • Installed new cable terminals for the connection of high voltage cells;
  • Installed new pivot and bushings;
  • Implemented new busbar aluminum busbar.

 